Preliminary economic assessment
Reported project economics for the 2026 PL Gold Mine PEA.
- After-tax NPV (5% discount rate)
- US$180.6M
- After-tax NPV (8% discount rate)
- US$151.4M
- After-tax IRR
- 111%
- LOM AISC
- US$2,288/oz
What the market pays for this NPV
Minnova Corp's market cap against the study's after-tax (5%) NPV.
- Market cap
- US$10.4M
- Study NPV
- US$181M
Whole company against the full project NPV, with no ownership adjustment. Share price 2026-11-20, FX 2026-11-20.
NPV at other gold prices
After-tax NPV (5%) in the study's own price cases. Click a case to see what the market pays at that price.
Base case pricesAu $3,000/ozUS dollars, as used in the PEA
| Figure | Base case | US$3,500/oz | US$4,000/oz |
|---|---|---|---|
| Gold price assumption | US$3,000/oz | US$3,500/oz | US$4,000/oz |
| After-tax NPV (5%) | US$180.6M | US$310.8M | US$438.9M |
| After-tax NPV (8%) | US$151.4M | US$260.1M | US$367.2M |
| After-tax IRR | 111% | 151.6% | 187.5% |
| After-tax payback from start of production | 0.68 years | 0.54 years | 0.45 years |
| Pre-tax NPV (5%) | US$283.4M | US$500.2M | US$717M |
| Pre-tax IRR | 143.1% | 201.8% | 254.6% |
| LOM after-tax free cash flow | US$247.6M | US$427.7M | US$604.9M |
| LOM taxes | US$139.6M | US$259.4M | US$382.1M |
| LOM AISC | US$2,288/oz | US$2,305/oz | US$2,323/oz |
An annual production schedule has not been verified for this study. Reported averages below are not a year-by-year forecast.
Explore NPV at your metal prices
Awaiting verified inputsThe calculator moves the reported NPV with metal prices, so it needs the study's year by year payable metal production (how many ounces or pounds are sold each year). So far we only have the PEA 2026 from the company's announcement or presentation, which give headline figures but not the yearly production table. That table is in the technical report, which Canadian companies must file within 45 days of announcing a study. The calculator switches on once that report is added.
The study's reported figures above are shown as published.
Mine life & production
- Mine life
- 10 years
- LOM taxes
- US$139.6M
- LOM total cash cost
- US$2,183/oz
- LOM all-in cost
- US$2,377/oz sold
- LOM recovered gold
- 621.5 koz
- LOM ore mined and processed
- 6.5 Mt
- LOM waste mined
- 40.3 Mt
- Average annual gold production, 2028–2037
- 62.2 koz
- Processing throughput in 2028
- 492,000 tonnes
- Processing throughput from 2029
- 720,000 tonnes per year
- Open-pit ore mined and processed
- 1.76 Mt
- Underground ore mined and processed
- 4.74 Mt
- Open-pit waste mined
- 36.9 Mt
- Underground waste mined
- 3.42 Mt
- Open-pit strip ratio
- 21 waste:ore
- Open-pit recovered gold
- 212 koz
- Underground recovered gold
- 409.4 koz
- Recovered gold in first two production years
- 165.4 koz
- Peak annual gold production in 2029
- 91.6 koz
- Processing rate from 2029
- ~2,000 tonnes per day
- Processing cost including mill power
- US$182.8M
- Processing cost including mill power per tonne milled
- US$28.13/t milled
- Shared site, G&A, camp, community and other cost
- US$154.4M
- Shared site, G&A, camp, community and other cost per tonne milled
- US$23.76/t milled
- Refining, transport and selling cost
- US$32/oz sold
- Royalty cost
- US$90/oz sold
- Manitoba mining tax
- US$53M
- Federal and Manitoba income tax
- US$86.6M
- 2026 MRE effective September 10, 2026 — Measured & Indicated resource tonnes at 0.60, 1.92 and 1.43 g/t Au cut-offs
- 3,757,026 tonnes
- 2026 MRE effective September 10, 2026 — Measured & Indicated resource gold grade at 0.60, 1.92 and 1.43 g/t Au cut-offs
- 4.98 g/t Au
- 2026 MRE effective September 10, 2026 — Measured & Indicated contained resource gold at 0.60, 1.92 and 1.43 g/t Au cut-offs
- 601,158 oz
- 2026 MRE effective September 10, 2026 — Inferred resource tonnes at 0.60, 1.92 and 1.43 g/t Au cut-offs
- 1,667,132 tonnes
- 2026 MRE effective September 10, 2026 — Inferred resource gold grade at 0.60, 1.92 and 1.43 g/t Au cut-offs
- 3.78 g/t Au
- 2026 MRE effective September 10, 2026 — Inferred contained resource gold at 0.60, 1.92 and 1.43 g/t Au cut-offs
- 202,810 oz
Cash flow, capital & returns
- After-tax payback from start of production
- 0.68 years
- LOM after-tax free cash flow
- US$247.6M
- Total LOM capital including sustaining and closure
- US$120.9M
- Pre-tax NPV (5% discount rate)
- US$283.4M
- Pre-tax IRR
- 143.1%
- Pre-production capital, 2026–2027
- US$53.4M
- Pre-production capital contingency rate
- 15%
- Pre-production capital contingency
- US$7M
- LOM total operating cost
- US$1,280.8M
- Sustaining capital
- US$62.9M
- Sustaining capital and closure cost
- US$105/oz sold
- Non-sustaining capital cost
- US$89/oz sold
- Open-pit direct operating cost
- US$217.1M
- Open-pit direct operating cost per tonne of ore
- US$123.58/t OP ore
- Open-pit direct operating cost per recovered ounce from source
- US$1,024/oz
- Underground direct operating cost
- US$726.5M
- Underground direct operating cost per tonne of ore
- US$153.18/t UG ore
- Underground direct operating cost per recovered ounce from source
- US$1,774/oz
- Total operating cost per tonne milled
- US$197.08/t milled
- Total operating cost per ounce sold
- US$2,061/oz sold
- Royalty rate on gross revenue
- 3%
Study assumptions, grades & recoveries
- LOM average plant head grade
- 3.3 g/t Au
- Gold price assumption
- US$3,000/oz
- Open-pit average plant head grade
- 4.68 g/t Au
- Underground average plant head grade
- 2.8 g/t Au
- Metallurgical recovery design
- 90%
- Plant head grade, 2028–2029
- 4.9 g/t Au
- Exchange rate
- US$0.74/C$
The PEA models a combined open-pit and underground operation using the existing processing plant. Results are on a 100% equity basis in real, unescalated US dollars. The PEA is preliminary, includes Inferred Mineral Resources, and does not define Mineral Reserves; there is no certainty that its results will be realized.