Mining project

Nueva Recuperada Project

Silver·Underground·Production·Peru

Operated by Silver X Mining Corp

Last reported
Jun 30, 2026

Quarter

Silver eq. produced
283,029 oz

Latest quarter

All-in sustaining cost
US$46.10/oz

per Silver eq. ounce

Mineral resources
May 31, 2025

NI 43-101

A 20,795-hectare district-scale mining project in Huancavelica integrating the producing Tangana Mining Unit, the development-stage Plata Mining Unit, exploration assets and centralized processing infrastructure.

Ownership

  • Owner · Nueva Recuperada Property

    Source SILVER X MINING CORP MANAGEMENT DISCUSSION AND ANALYSIS OF PRODUCTION AND FINANCIAL RESULTS · Mar 31, 2026

  • Operator · runs the project, does not imply ownership · Ongoing mining operations and production decision

    Source SILVER X ENGAGES INDEPENDENT STRATEGIC CONSULTING FIRM AND APPOINTS GENERAL MANAGER · Oct 30, 2025

Resources and reserves

How this data is collected

Estimates as reported by the company. Tonnages and contained metal are shown in one unit per column so they can be compared; the figure as published is on each one. Select a category to value its rows on your own price and recovery assumptions.

Mineral resources as at May 31, 2025NI 43-101

Nueva Recuperada Property Combined

CategoryTonnageMtGradeContained metal
Silveroz/tGoldg/tLead%Zinc%Copper%Silver eq.oz/tSilverMozGoldkozLeadktZincktCopperktSilver eq.Moz
Measured1.633.090.6912.462.770.188.565.0536.2840.145.172.9913.98
Indicated2.153.90.2862.283.130.118.628.398.3949.0767.442.4318.57
Measured & indicated3.793.550.4612.352.970.148.5913.4413.4489.16112.615.4232.55
Inferred15.114.510.2651.491.720.067.0368.9171.14225.44259.298.99109.53

Cut-off 60 US$/t

Breakdown by deposit (5) — restates the totals above, not additional to them

All other veins

CategoryTonnagektGradeContained metal
Silveroz/tGoldg/tLead%Zinc%Copper%Silver eq.oz/tSilverkozGoldkozLeadktZincktCoppertSilver eq.koz
Measured126.324.070.4641.692.010.17.525141.892.142.54126949.52

Cut-off 60 US$/t

All Other Veins

CategoryTonnageMtGradeContained metal
Silveroz/tGoldg/tLead%Zinc%Copper%Silver eq.oz/tSilverMozGoldkozLeadktZincktCopperktSilver eq.Moz
Indicated0.3143.80.3912.672.90.148.841.193.958.389.110.442.78
Inferred8.535.440.3731.481.360.077.6546.38102.26126.19115.955.9765.26

Cut-off 60 US$/t

Ccasahuasi

CategoryTonnageMtGradeContained metal
Silveroz/tGoldg/tSilver eq.oz/tSilverkozGoldkozSilver eq.Moz
Inferred1.410.50.9362.370342.33.23

Cut-off 0.25 g/t

Plata

CategoryTonnageMtGradeContained metal
Silveroz/tLead%Zinc%Silver eq.oz/tSilverMozLeadktZincktSilver eq.Moz
Indicated0.8915.322.133.79.484.7418.9432.988.44
Inferred53.411.382.275.9917.0668.73113.4529.93

Cut-off 60 US$/t

Tangana

CategoryTonnageMtGradeContained metal
Silveroz/tGoldg/tLead%Zinc%Copper%Silver eq.oz/tSilverMozGoldkozLeadktZincktCopperktSilver eq.Moz
Measured1.513.010.712.522.830.198.654.5434.3937.9642.632.8613.03
Indicated0.9492.590.522.292.670.217.742.4615.8821.7425.351.997.35
Inferred1.592.990.521.921.880.1974.7526.5830.5229.883.0211.12

Cut-off 60 US$/t

Source AGX_2025_NI43101_PEA_Technical_Report_ _Combined_Plata_and_Tangana · May 31, 2025

Shaded columns are equivalent figures. An equivalent column combines the metals beside it on the company's own price assumptions. It is not additional metal and must not be added to them.

Figures as published by the company, in the units they were reported in. The latest period is open; select any other to expand it.

PeriodSilver eq. producedSilver priceAISC / ozRevenue
Q2 2026Quarter283,029 ozUS$72.67/ozUS$46.10/ozUS$17.3M

Reported as "2Q26"

Ore mined
67,439 t
Ore processed
62,252 t
Cash cost
US$156.10/t
All-in sustaining cost
US$209.61/t
Revenue
US$17.30M
ReportedSilverGoldLeadZincSilver eq.
Metal produced145,885 oz1,404 oz283,029 oz
Realized priceUS$72.67/ozUS$4,505/ozUS$0.89/lbUS$1.49/lb
Cash costUS$34.33/oz
All-in sustaining costUS$46.10/oz
AgEq ounces processed380,436 oz

Source Silver X Mining Corp. Reports Record 2Q26 Revenue of $17.3M, Up 29% Over 1Q26, and $7.7M of First-Half Net Income · Aug 6, 2026

Q1 2026Quarter179,941 ozUS$91.39/ozUS$53.24/ozUS$13.4M

Reported as "1Q26"

Ore mined
40,946 t
Ore processed
44,883 t
Cash cost
US$151.71/t
All-in sustaining cost
US$213.43/t
Operating revenue (gross)
US$815,402
Operating revenue (gross)
US$3,825,257
Operating revenue (gross)
US$13,919,082
Operating revenue (net)
US$13,430,763
Operating revenue (gross)
US$1,027,780
Operating revenue (gross)
US$8,250,643
ReportedSilverGoldLeadZincSilver eq.
Head grade86.8 g/t1 g/t1.2%1.3%
Recovery84%60%80%72%
Metal produced105,988 oz679 oz996,022 lb957,293 lb179,941 oz
Metal sold98,949 oz790 oz946,046 lb915,825 lb172,369 oz
Payable metal90,277 oz745 oz876,611 lb753,042 lb
Realized priceUS$91.39/ozUS$5,131/ozUS$0.93/lbUS$1.36/lb
Cash costUS$37.84/oz
All-in sustaining costUS$53.24/oz
Metal processed125,195 oz1,419 oz1,222,087 lb1,279,787 lb
Average AgEq head grades5.6 oz/t175.4 g/t
AgEq processed253,114 oz

Source SILVER X MINING CORP MANAGEMENT DISCUSSION AND ANALYSIS OF PRODUCTION AND FINANCIAL RESULTS · Mar 31, 2026

Q3 2025Quarter166,621 ozUS$39.90/ozUS$36.80/ozUS$4.96M

Reported as "3Q25"

Ore mined
28,525 t
Ore processed
33,505 t
Cash cost
US$144.00/t
All-in sustaining cost
US$183.10/t
Operating revenue (gross)
US$815,177
Operating revenue (gross)
US$946,193
Operating revenue (gross)
US$5,478,006
Operating revenue (gross)
US$788,536
Operating revenue (net)
US$4,955,703
Operating revenue (gross)
US$2,928,100
ReportedSilverGoldLeadZincSilver eq.
Head grade87.6 g/t0.7 g/t1.4%1.4%6.8 oz/t211 g/t
Recovery84%50%82%76%
Metal produced80,121 oz398 oz860,934 lb776,331 lb166,621 oz
Metal sold80,923 oz237 oz902,998 lb867,191 lb149,999 oz
Payable metal73,305 oz207 oz1,069,052 lb717,889 lb
Realized priceUS$39.90/ozUS$3,938/ozUS$0.90/lbUS$1.10/lb
Cash costUS$28.90/oz
All-in sustaining costUS$36.80/oz
Metal processed94,395 oz751 oz1,046,635 lb1,021,443 lb
AgEq processed227,315 oz

Source 2025_09_30 Silver X Mining Corporation MDA Final · Sep 30, 2025

Shaded columns are equivalent figures. An equivalent column combines the metals beside it on the company's own price assumptions. It is not additional production and must not be added to them.