Preliminary economic assessment
Reported base-case project economics for the 2026 PEA.
- Post-tax NPV (5% discount rate)
- 762.7US$M
- Post-tax IRR
- 41%
- Initial capital including closure deposit
- 332.2US$M
- All-in sustaining cost
- 18.74US$/oz Ag
Market cap / after-tax (5%) NPV
11.5%Kootenay Silverof after-tax (5%) project NPV
Market cap US$87.9M · NPV US$762.7M · Share price 2026-09-21 · FX 2026-09-22. Whole company compared with the full project NPV; no ownership adjustment.
Metal prices the company used in this PEA
- Silver
- $50/oz
- Gold
- $3,611/oz
- Lead
- $0.91/lb
- Zinc
- $1.25/lb
All prices in US dollars.
Production through the mine life
Payable metal by operating period, including reported ramp-up and partial years.
- Peak annual output
- 6.32
- Operating periods shown
- 14
Moz Ag · operating period 1
Includes reported ramp-up and partial years
Silver · Moz Ag per operating period
Operating period
View annual figures
| Operating period | Silver (Moz Ag) |
|---|---|
| 1 | 6.3212 |
| 2 | 5.2011 |
| 3 | 5.223 |
| 4 | 4.4809 |
| 5 | 4.5837 |
| 6 | 4.0223 |
| 7 | 4.3068 |
| 8 | 4.3624 |
| 9 | 4.5386 |
| 10 | 4.2408 |
| 11 | 4.0453 |
| 12 | 4.1882 |
| 13 | 3.8997 |
| 14 | 4.25 |
Annual payable metal production from the base-case cash-flow table, rather than gross metal produced.
Source La Cigarra 43-101 Pre Economic Assessment (14.33 MB) · PDF page 261 · Jul 21, 2026
Mine life & production
- Mine life
- 14 years
- LOM total payable silver production
- 63,663.9 koz
- LOM total payable gold production
- 27.3 koz
- LOM total payable lead production
- 45.3 Mlb
- LOM total payable zinc production
- 48.5 Mlb
- Operating cash cost
- 16.85 US$/oz Ag
- LOM EBITDA
- 2,342 US$M
Cash flow, capital & returns
- Post-tax payback period
- 1.9 years
- LOM pre-tax free cash flow
- 1,896.9 US$M
- LOM post-tax free cash flow
- 1,165.9 US$M
- LOM sustaining capital
- 79.7 US$M
- Pre-tax NPV (5% discount rate)
- 1,264.9 US$M
- Pre-tax IRR
- 55 %
- Pre-tax payback period
- 1.7 years
Study assumptions, grades & recoveries
- Silver price assumption
- 50 US$/oz
- Gold price assumption
- 3,611 US$/oz
- Lead price assumption
- 0.91 US$/lb
- Zinc price assumption
- 1.25 US$/lb
- LOM average silver head grade
- 78.7 g/t
- LOM average lead head grade
- 0.13 %
- LOM average zinc head grade
- 0.18 %
- LOM average gold head grade
- 0.06 g/t
- Oxide silver recovery
- 88.3 %
- Sulphide silver recovery
- 89.3 %
- Oxide gold recovery
- 37.5 %
- Sulphide gold recovery
- 61.8 %
The economic analysis uses base-case silver, gold, lead and zinc prices and a 5.00% discount rate; all monetary values are reported in U.S. dollars.
Source La Cigarra 43-101 Pre Economic Assessment (14.33 MB) · PDF page 256 · Jul 21, 2026
Source La Cigarra 43-101 Pre Economic Assessment (14.33 MB) · PDF page 21 · Jul 21, 2026